This problem tests your ability to model complex system dependencies as a directed graph and determine the minimum time to complete a set of tasks given sequential constraints.

Task Scheduling with Dependencies

You are given a list of tasks, where each task is defined as a tuple (id, duration, prerequisites).

  • id: A unique integer representing the task.
  • duration: An integer representing the time required to complete the task.
  • prerequisites: A list of task IDs that must be completed before this task can start.

Your goal is to calculate the minimum time required to complete all tasks, assuming you have an unlimited number of workers available. If a circular dependency exists, return -1.

Function Signature

def min_completion_time(tasks: List[Tuple[int, int, List[int]]]) -> int:

Constraints

  • Number of tasks: 1 to 10,000.
  • Task durations: 1 to 1,000.
  • Circular dependencies are possible.

Example 1

Input: [(1, 3, []), (2, 2, [1]), (3, 4, [1])] Output: 7 Explanation: Task 1 (3 units) starts at time 0. Tasks 2 and 3 can start at time 3. Task 2 finishes at 3+2=5. Task 3 finishes at 3+4=7. Max time is 7.

Example 2

Input: [(1, 5, [2]), (2, 5, [1])] Output: -1 Explanation: Circular dependency detected between 1 and 2.

Edge Cases

  • Disconnected graph components.
  • Tasks with no prerequisites.
  • Single task scenarios.

Hints

Hint 1

Represent the tasks as a Directed Acyclic Graph (DAG) where an edge from A to B means A must finish before B starts.

Hint 2

Use Kahn's algorithm or DFS with recursion stack tracking to detect cycles and calculate the longest path in the graph.

Hint 3

The completion time for a task is its own duration plus the maximum completion time of all its prerequisites.

Follow-up questions

  • How would your solution change if you were limited to only 2 workers?
  • If each task had a 'priority' score, how would you modify the execution order to prioritize higher-value tasks given the same dependency constraints?
  • How would you optimize the memory footprint if the task list contained millions of nodes?