This problem tests your ability to perform a Kahn’s algorithm-based topological sort while grouping tasks into parallelizable layers, ensuring cycle detection and dependency validation.

Problem Statement

You are tasked with building a dependency manager for a task-based build system. You are given n tasks, labeled 0 to n-1, and a list of dependencies where [u, v] indicates that task u must be completed before task v can begin.

Your goal is to return the tasks grouped by "levels." A task can be assigned to a level if all its dependencies have been completed in previous levels. Tasks with no dependencies belong in level 0. If a valid ordering is impossible due to a circular dependency, return an empty list.

Function Signature

def get_build_levels(n: int, dependencies: List[List[int]]) -> List[List[int]]:

Constraints

  • 1 <= n <= 10,000
  • 0 <= len(dependencies) <= 100,000
  • dependencies[i] are distinct pairs.

Examples

Example 1: Input: n = 4, dependencies = [[0, 1], [0, 2], [1, 3], [2, 3]] Output: [[0], [1, 2], [3]] Explanation: Task 0 starts at level 0. Tasks 1 and 2 depend on 0, so they start at level 1. Task 3 depends on 1 and 2, starting at level 2.

Example 2: Input: n = 2, dependencies = [[0, 1], [1, 0]] Output: [] Explanation: A cycle exists (0 -> 1 -> 0), so no valid order exists.

Edge Cases

  • Disconnected components (e.g., tasks with no dependencies that don't relate to each other).
  • n = 1 with no dependencies.
  • Empty dependencies list.

Hints

Hint 1

Represent the dependencies as an adjacency list and keep an array to track the 'in-degree' (number of incoming dependencies) of each task.

Hint 2

Initialize a queue with all nodes that have an in-degree of 0; these represent the current level.

Hint 3

For each level, process all nodes currently in the queue, decrement the in-degree of their neighbors, and if a neighbor's in-degree reaches 0, add it to the queue for the next level.

Follow-up questions

  • How would you modify this algorithm to return the total number of levels, or the 'depth' of the dependency graph?
  • If some tasks take different amounts of time to complete, how would you calculate the minimum time required to complete all tasks assuming you have infinite parallel workers?
  • What is the time and space complexity of this approach, and can it be optimized if the graph is sparse?