Level-Ordered Dependency Build Order
RobloxMachine Learning Engineer · Technical ScreenLast updated
This problem tests your ability to perform a Kahn’s algorithm-based topological sort while grouping tasks into parallelizable layers, ensuring cycle detection and dependency validation.
Problem Statement
You are tasked with building a dependency manager for a task-based build system. You are given n tasks, labeled 0 to n-1, and a list of dependencies where [u, v] indicates that task u must be completed before task v can begin.
Your goal is to return the tasks grouped by "levels." A task can be assigned to a level if all its dependencies have been completed in previous levels. Tasks with no dependencies belong in level 0. If a valid ordering is impossible due to a circular dependency, return an empty list.
Function Signature
def get_build_levels(n: int, dependencies: List[List[int]]) -> List[List[int]]:
Constraints
1 <= n <= 10,0000 <= len(dependencies) <= 100,000dependencies[i]are distinct pairs.
Examples
Example 1:
Input: n = 4, dependencies = [[0, 1], [0, 2], [1, 3], [2, 3]]
Output: [[0], [1, 2], [3]]
Explanation: Task 0 starts at level 0. Tasks 1 and 2 depend on 0, so they start at level 1. Task 3 depends on 1 and 2, starting at level 2.
Example 2:
Input: n = 2, dependencies = [[0, 1], [1, 0]]
Output: []
Explanation: A cycle exists (0 -> 1 -> 0), so no valid order exists.
Edge Cases
- Disconnected components (e.g., tasks with no dependencies that don't relate to each other).
n = 1with no dependencies.- Empty
dependencieslist.
Hints
Hint 1
Represent the dependencies as an adjacency list and keep an array to track the 'in-degree' (number of incoming dependencies) of each task.
Hint 2
Initialize a queue with all nodes that have an in-degree of 0; these represent the current level.
Hint 3
For each level, process all nodes currently in the queue, decrement the in-degree of their neighbors, and if a neighbor's in-degree reaches 0, add it to the queue for the next level.
Follow-up questions
- How would you modify this algorithm to return the total number of levels, or the 'depth' of the dependency graph?
- If some tasks take different amounts of time to complete, how would you calculate the minimum time required to complete all tasks assuming you have infinite parallel workers?
- What is the time and space complexity of this approach, and can it be optimized if the graph is sparse?