Implement a Dependency-Aware Task Scheduler
Scale AISoftware Engineer · Technical ScreenLast updated
This question evaluates skills in dependency management, deadline-driven scheduling and algorithmic data-structure design, focusing on handling directed acyclic graphs and ordering constraints.
Implement a TaskManager class with two methods:
AddTasks(tasks): add one or more tasks into the system.ConsumeTask(): return and remove the executable task with the earliest deadline.
Each task has the following fields:
id: unique task identifierddl: integer deadline, where a smaller value means an earlier deadlinesubTasks: a list of prerequisite task IDs that must be completed before this task can be consumed
Requirements:
- Support multiple calls to
AddTasks. ConsumeTask()should return the pending task with the smallest deadline among all currently executable tasks.- A task is executable only if all of its prerequisite tasks have already been consumed.
- If no executable task exists, return
NO_TASK. - For this coding problem, assume task IDs are unique and the dependency graph is valid and acyclic.
Explain the data structures you would use and implement both methods efficiently.