Compute minimal time to finish dependent tasks
UberMachine Learning Engineer · OnsiteLast updated
This question evaluates understanding of graph algorithms and scheduling, specifically reasoning about task dependencies, parallel execution, and cycle detection in directed graphs.
Coding: Task Scheduling With Prerequisites (Parallel Allowed)
You have n tasks labeled 1..n. Each task takes exactly 1 unit of time to complete. Some tasks have prerequisites.
You are given a list of prerequisite pairs deps, where each pair [a, b] means:
- Task
amust be completed before taskbcan start.
You can run any number of tasks in parallel as long as their prerequisites are satisfied.
Input
- Integer
n. - 2D array/list
depsof pairs[a, b].
Output
Return the minimum total time (number of time units) required to finish all tasks.
Notes
- If the dependency graph contains a cycle (tasks cannot be completed), specify what you would return (e.g.,
-1) and implement accordingly.
Example
If n = 3 and deps = [[1,3],[2,3]], tasks 1 and 2 can run in parallel in time 1, then task 3 runs in time 2, so the answer is 2.