Plan CI Build Job Order with Prerequisites, Urgency and Filters
RipplingSoftware Engineer · Technical ScreenLast updated
Order CI build jobs so that prerequisites come first, more urgent jobs go earlier, filtered-out jobs are skipped without breaking ordering through them, and jobs can be grouped into parallel waves. Tests Kahn's algorithm, deterministic tie-breaking, cycle reporting, and turning a detailed spec into code.
Your team's CI system receives a list of build jobs for each commit and must decide the order in which to dispatch them. The spec has many small rules. None of them is hard on its own, but together they are easy to get subtly wrong, so make every rule explicit and testable.
Each job looks like:
{"id": "test", "needs": ["compile"], "urgency": 4, "tags": ["slow"]}
needs lists jobs that must be dispatched earlier. A higher urgency is more important.
Part 1: Prerequisites first
plan(jobs, by_urgency=False) -> list[str] returns every job id so that each job comes after everything it needs. When several jobs are available, pick the one that appears earliest in the input. Raise an error for duplicate ids, unknown prerequisites, and cycles, and report one actual cycle path (for example x -> z -> y -> x).
Part 2: Urgency
With by_urgency=True, the next job is the available one with the highest urgency, with ties going to input order. Urgency never lets a job jump ahead of its prerequisites, and it does not pull prerequisites forward.
Part 3: Filters
plan(jobs, filters=[...]) takes predicates. A job is kept only if all of them return True. Excluded jobs are not output, but ordering through them is preserved: if kept job D needs excluded job B, and B needs kept job A, then D must still come after A.
Part 4: Parallel waves
waves(jobs) -> list[list[str]] groups jobs into stages. Wave 0 holds jobs with no prerequisites, and each later wave holds jobs whose prerequisites are all in earlier waves. Place each job in the earliest possible wave, and sort jobs within a wave by urgency (descending) and then input order.
Example
fetch needs [] urgency 1
compile needs [fetch] urgency 3
lint needs [fetch] urgency 5 tags [style]
test needs [compile] urgency 4
docs needs [] urgency 2 tags [docs]
package needs [test, lint] urgency 2
publish needs [package, docs] urgency 9
Part 1: fetch, compile, lint, test, docs, package, publish
Part 2: docs, fetch, lint, compile, test, package, publish
Part 3 (drop tags docs and style): fetch, compile, test, package, publish
Part 4: [docs, fetch], [lint, compile], [test], [package], [publish]
Constraints
- Up to 10^4 jobs and 10^5 prerequisite edges. Aim for O((V + E) log V).
- Output must be deterministic for a given input.
Hints
Hint 1
Which jobs could be output right now? How does outputting one change that set?
Hint 2
Keep the available jobs in a heap. The heap key is where input order and urgency rules live.
Hint 3
If some jobs are never available, they are on or behind a cycle. Search only among them to report it.
Hint 4
For filters, compute for each kept job the nearest kept prerequisites reachable through excluded jobs, then schedule the reduced graph.
Follow-up questions
- How would you let an urgent job pull its prerequisites ahead of other available jobs?
- Jobs have estimated durations and you have 4 runners. How would you minimize total wall-clock time?
- Jobs arrive incrementally while others are running. How do you update the plan without recomputing everything?
- How would you support OR-combined filter groups specified in a config file?