Assign Minimum Workers to Jobs
LyftSoftware Engineer · Online AssessmentLast updated
This problem tests your ability to manage overlapping intervals and greedy resource allocation using minute-based time arithmetic.
Problem Statement
You are tasked with assigning workers to a series of jobs. Each job has a start time, an end time, and a required number of workers. A worker can only handle one job at a time. Once a worker finishes a job, they are immediately available for another. Your goal is to determine the minimum number of workers required to complete all jobs.
Time is provided in HH:MM format (24-hour clock). A job starting at 10:00 and ending at 11:00 occupies workers during the interval [600, 660) minutes from the start of the day.
Function Signature
def min_workers_required(jobs: List[Tuple[str, str, int]]) -> int:
jobs: A list of tuples, where each tuple is(start_time, end_time, worker_count).
Constraints
start_timeandend_timeare in "HH:MM" format.- Jobs are guaranteed to have
start_time < end_time. - The number of jobs is between 1 and 1000.
Examples
Example 1:
Input: [('09:00', '10:00', 2), ('09:30', '10:30', 1)]
Output: 3
Explanation: At 09:30, we need 2 workers for the first job and 1 for the second, totaling 3.
Example 2:
Input: [('08:00', '09:00', 1), ('09:00', '10:00', 1)]
Output: 1
Explanation: The first worker finishes at 09:00 and is immediately free to take the second job.
Edge Cases
- Jobs that end exactly when another begins.
- Jobs that span across the full day.
- A single job requiring multiple workers.
Hints
Hint 1
Convert all time strings to total minutes from the start of the day (HH * 60 + MM) to simplify interval arithmetic.
Hint 2
Consider using the 'sweep-line' algorithm: create events for both the start and end of each job, marking worker requirements as positive at the start and negative at the end.
Hint 3
Sort the events by time; if two events occur at the same time, process the 'end' event before the 'start' event to account for immediate worker availability.
Follow-up questions
- How would your approach change if workers require a 15-minute 'cooldown' period between jobs?
- If each worker had a limited total capacity (e.g., maximum 8 hours per day), how would you modify the algorithm?
- What is the time complexity of your solution, and can it be optimized using a min-heap?